Proposed Project Schedule
-
Dec1 & 2December 1 & 2, 2015PublicĀ Open Houses
-
Feb2016February 2016Route Alternatives Submitted to PUCT
-
Fall2016Fall 2016PUCT Decision
-
TBA20172017Easement Acquisition
-
TBA20172017Environmental Permitting
-
TBA20182018Construction
-
TBA20212021Estimated In-Service Date